Wasted Stimulus Work Leaves River Rocks Blocking Barges

Lock
This article is for subscribers only.

In 2009, the U.S. Army Corps of Engineers, seeking a method less expensive and damaging to wildlife than dynamiting to clear rocks from the Mississippi River, committed $5.7 million to an experimental grinding process.

The project, financed by President Barack Obama’s economic stimulus program, was futile and called off after two efforts, one in 2011 and another earlier this year, totaling about four weeks.